Construction is well under way and on schedule. Foundations are in and the 1st floor is going up

     

 

November 2007.
Construction is now well under way on the 1st floor and 2nd floor is commencing. All is going well without issues or complications. There are no workers on site in these photos as we shot them mid day during lunch time. These 1st few phases are generally without much detail but as the project continues and becomes more interesting we will upload larger photo sets.

Also, my architect and administrator visited the site with me and you will see us having lunch in our favorite Taiba beach restaurant. Fresh fish, salads, rice dishes, shrimp stew, juices and fruits listening to Bossa Nova and looking at Taiba beach.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2  

 

February 2008.
Construction is progressing well and is mainly structural. The 3rd floor is now well under way and some units are also being plastered. All site retaining has been done and shortly the pool area will commence. The roof is the next milestone.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2

 

March 2008.
3rd floor is completing.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2

 

June 2008.
3rd floor is complete and Roof is under way. Tiling and rendering are under way. The beach equipment storage and wash down area is now being constructed.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2

 

August 2008.
Internal joinery and tiling is near complete and the external joinery will now commence.
Kite storage and laundry building is under way.

TBG 2 TBG 2 TBG 2
 

November 08.
Kite shed is complete. External joinery has been installed and tiling, services nearly complete. Pool has commenced as has the gym/spa.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2
 

February 2009.
The super structure is now fully complete. Tiling is completing. Paving and landscaping is beginning. Site services are being installed.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2
 

April 2009.
The construction is proceeding quicker now. Rendering and painting is in final stages. Tiling is going well and pathways, pool, public areas are completing. You can see the new neighbor of Taiba projects, the new Pousada which we are pleased to report has an excellent restaurant for our clients to use.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2
 

August 2009
Construction is ending now and final details are at work. Hand rails are being installed and landscape design is starting. The pool is being cleaned now also and the gym and saunas are being completed.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2
 

September 2009
Construction is complete and apartments and buildings are ready.
We are just completing the landscape gardens now.
You are invited to inspect your unit at your convenience.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
 

January 2010
The project continues to be tidied up and final touches are in place such as landscaping, pool maintenance etc.

TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
TBG 2 TBG 2 TBG 2 TBG 2 TBG 2 TBG 2
 

February 2010
The gardens continue to mature, the front wall has been modified, pool still blue and warm, the beach still great. Gym will shortly get a 2nd round of items.
Clients are in and using their units, pool, beach and the great BBQ.